County Highway Work Announced

And, this isn’t an April Fool’s Day story. Rather it is a press release from the McHenry County Transportation Department:

Highway improvements scheduled by the McHenry County Transportation Department this year. (Click to enlarge.)

The McHenry County Division of Transportation is proud to announce the 2010 interactive construction map at  mchenrycountydot.org.

The key to map.

This map will allow the public user to see at a glance all of the County construction project locations, as well as more detailed project information on any particular project. This can be done by clicking on the identify (i) icon and then clicking on the highlighted portion of the roadway. If more detailed information is desired, contact information is included for your use. This map was produced through the assistance of the County’s Geographical Information System (GIS) Department.

Construction Projects

Kishwaukee Valley Road Bridge Replacement

This project will replace the bridge originally constructed in 1953 with a two-span prestressed concrete 36-inch deep I-beam bridge, with a poured in-place 8-inch thick concrete deck, spanning 123-feet in length. It includes approach pavement, milling and resurfacing, shoulder widening and guardrail placement.

Kishwaukee Valley Road was closed to thru traffic starting on February 1, 2010 between Hughes Road and Menge Road. Access up to the bridge is maintained for local traffic only. A marked detour is provided using Hughes Road, U.S. Route 14, Dunham Road and Menge Road. (click here for the detour map).

This project is scheduled to be completed approximately June 12, 2010.

Alden Road Bridge Replacement and Roadway Improvements

This project will replace the existing bridge built in 1939, with a 58-foot long by 40-foot wide, single-span poured in-place concrete bridge deck, on seven, 36-inch deep precast prestressed concrete I-beams.

This project also includes complete pavement and drainage feature reconstruction from about 600 feet south of Illinois Route 173 to about 1,800 feet north of Illinois route 173. Driveways and sidewalks within the project limits will be replaced and a new drainage system will be installed throughout. Along with the new pavement, curb & gutter will be provided to improve drainage. Two special Stormwater Treatment Structures will be installed before stormwater enters the creek to protect water quality.

The Project will be built using stage construction (one side at a time) and will require a temporary traffic signal to limit the bridge to one-way traffic for the duration of the project. Two-way traffic will be maintained on the roadway portion using temporary pavement.

Work on the project started approximately February 22, 2010 and the project has an October 31, 2010 completion date.

Virginia Road Reconstruction

This project will reconstruct Virginia Road between Rakow Road and Illinois Route 31, with the exception of the new pavement recently constructed in connection with the Waste Transfer Facility, and the intersection at Illinois Route 31, which will be done as a separate future project.

This project will be constructed using Stage construction, maintaining one–way traffic southeast bound only (Rakow Road to Illinois Route 31) for the duration of the construction. Northwest bound traffic will be detoured on Illinois Route 31 to the north and then west on Rakow Road back to Virginia Road.

The contractor plans to start work around April 19, 2010 and the project completion date is July 2, 2010.

Walkup Road Widening, Resurfacing and Shared-use Path Construction

This project will provide pavement widening to extend the three-lane section of pavement from Dvorak Drive through Crystal Springs Road, add traffic signals at Pleasant Hill Road, Edgewood Road and Crystal Springs Road, add right and left turn lanes at intersections, and resurface the roadway in this area. In addition, a shared-use path will be constructed between Veteran Acres Park and Pleasant Hill Road on the east side of the roadway to enhance safety for pedestrians and bicyclists in the area.

Beginning in December 2009, public utility relocation work was started with the intent to move existing utilities out of conflict with the new roadway, path and storm sewers prior to construction to avoid delays. The contractor is expected to start construction around May 1, 2010 and project completion is expected in the summer of 2011.

Two-way traffic will be maintained throughout utilizing stage construction with daily or periodic lane closures as required using flaggers. This work will create delays and traffic disruption at times.

Federal Congestion Mitigation & Air Quality (CMAQ) funds will pay for 80% of the design and construction of this project and the 20% local match will use McHenry County Division of Transportation funds.

A project website (www.walkuproad.info) will be available to ask questions, get project updates, and obtain project information.

Rakow Road Widening, Relocation & Reconstruction

This project is currently in the Land Acquisition and Final Design stages. A summer 2010 letting is desired but is dependent upon the completion of the needed right-of-way purchases. It is anticipated that two construction seasons will be necessary to complete this project which is estimated to cost approximately 30 million dollars.

This project will relocate Rakow Road to the east of it’s current alignment starting at McHenry Avenue to soften the curve to the north and east.

It will also provide three thru-lanes of traffic in each direction from Ackman Road to Pyott Road, and dual left-turn lanes at Ackman Road, McHenry Avenue, Pyott Road, Pingree Road and Illinois Route 31.

Two thru-lanes in each direction will be constructed from Pyott Road to Illinois Route 31, and a pedestrian/bike path bridge will be constructed over Rakow Road for the McHenry County Conservation District’s Prairie Trail Path. Public Utility coordination is currently underway.

A project website will be available in the future to ask questions, get project updates, and obtain project information.

Pavement Preservation Projects

County Paving (Milling and Resurfacing) Project

This project includes milling and resurfacing on various County Highways as highlighted on the map in green. The project includes milling to a depth of 3.75” and patching any deteriorated pavement as needed. Then priming and placing a 2.25” lift of Binder Course followed by a 1.5” lift of Surface Course. Shoulder gravel will be added and thermoplastic pavement markings will be placed. The milled pavement material (RAP) is all recycled and re-used as aggregates in the new Hot Mix Asphalt.

The roads to be resurfaced under this project include:

  • Nelson and Deep Cut Roads between U.S. Route 14 and Charles/Alden Road
  • Hartland Road from U.S. Route 14 to Nelson Road
  • Hobe Road from South Street to Kishwaukee Valley Road
  • River Road between Illinois Route 176 and Lily Lake Road
  • Ramer Road from Oak Grove Road to Lawrence Road
  • Oak Grove Road from Illinois Route 173 to Ramer Road
  • Charles Road, a short repair section just west of Illinois Route 47

This project will resurface 20 lane miles of roadway at a bid cost of $2,560,270.95.

Work on this project is expected to start about May 31, 2010 and has a contract completion date of August 6, 2010. The impact to traffic will be daily lane closures in the immediate work area using flaggers to control one-way traffic thru the work zone. These temporary lane closures will take place throughout the various stages of the project and should generally minimize delays to a short duration.

Chapel Hill Road Resurfacing (ARRA Project)

These signs will pop up on Chapel Hill Road. This one is on Route 14 in Crystal Lake near The Freeze.

This project is funded through The American Recovery and Reinvestment Act and will mill and resurface four sections of Chapel Hill Road that fall between previous intersection improvements. The actual project length is a total of approximately 1.9 miles between Miller Road and Johnsburg Road at a bid cost of $568,605.96.

Work on this project is expected to start around June 1, 2010 and has a 25 working day duration or five to six weeks to complete. This work will essentially be the same as described above for milling and resurfacing in terms of work methods and traffic impacts.

Crack Sealing Contract

This project includes routing and sealing cracks in the pavement using a hot applied rubberized filler material. This work is done to extend the life of newer pavements by minimizing the water intrusion into the pavement and base material, thus lessening the severity of the effects of freeze-thaw cycles.

Crack sealing will be done on the following roads in 2010:

  • Kishwaukee Valley Road from the west County Line to U.S. Route 14
  • Vermont Road between Garden Valley Road and Kishwaukee Valley Road
  • Coral Road from Illinois Route 23 to South Union Road
  • Hunter Road from County Line Road to White Oaks Road
  • White Oaks Road between Illinois Route 173 and Hunter Road

If quantity remains in the contract after completion of those routes, Genoa Road and Harmony Road east of U.S. Route 20 will be treated to the extent possible.

This contract will crack seal about 42 lane miles of County Highways at a total bid cost of $125,211.06. The impact to traffic will be daily lane closures in the immediate work area using flaggers to control one-way traffic thru the moving work zone, and traffic delays should be minimal.

Microsurfacing Project

The 2010 project is still under development as the McHenry County Division of Transportation is working to create new mix designs using a more durable aggregate material than what is currently readily available locally. The project is anticipated to be ready for bidding in May with construction taking place later in the summer.

The road planned for this year is Charles Road from Nelson Road to Illinois Route 120. This includes about 8 lane miles of roadway at an estimated cost of $250,000. The 2009 microsurfacing project was not completed last year, but should be completed by the contractor in May, which includes work on Roberts Road and Altenberg Road.

The traffic impact of the microsurfacing work is more severe than paving due to the fact that the cure time of the microsurface material ranges from 30 to 90 minutes. Traffic must be kept off of the material during this time, creating long stretches of single-lane closures for the duration of curing time. Efforts will be made to minimize delays but due to the nature of the work, delays encountered could be significant.

Website Updates

Please visit our website at www.mchenrycountydot.org for periodic updates and for newly launched project specific websites.

Remember – Please drive safely in construction zones and watch out for workers!!


Comments

County Highway Work Announced — 1 Comment

  1. How much money did they waste on those signs?
    Way to go IDOT…

Leave a Reply

Your email address will not be published. Required fields are marked *